{"id":24380,"date":"2023-12-04T05:10:16","date_gmt":"2023-12-04T05:10:16","guid":{"rendered":"http:\/\/www.16news.com.au\/?p=24380"},"modified":"2023-12-04T05:10:16","modified_gmt":"2023-12-04T05:10:16","slug":"rail-repair-plan-hits-halfway-mark-on-a-high","status":"publish","type":"post","link":"http:\/\/www.16news.com.au\/index.php\/2023\/12\/04\/rail-repair-plan-hits-halfway-mark-on-a-high\/","title":{"rendered":"Rail Repair Plan hits halfway mark on a high"},"content":{"rendered":"\n<p>The Sydney Trains Rail Repair Plan is reaching great heights, as the project hits the halfway mark ahead of schedule with trackwork on the Sydney Harbour Bridge.<\/p>\n\n\n\n<p>The $97 million program, announced by the Transport Minister in June to improve the reliability and resilience of the network, has now seen 80% of the 1,900 high-priority defects fixed.<\/p>\n\n\n\n<p>For the 1.4 million people who cross the Harbour Bridge by train every week, the rail line is on track to be more resilient than ever before.<\/p>\n\n\n\n<p>This weekend, Rail Repair trackwork on this line has culminated in the installation of a new back-up airline hose across the bridge for the first time in history, meaning trains can keep running while critical signalling repairs are made.<\/p>\n\n\n\n<p>This work over the harbour comes as train testing on the Sydney Metro City and Southwest line ramps up deep below, as well as trackwork this weekend, to provide a world-class rail service for our city from 2024.<\/p>\n\n\n\n<p>At the 6-month mark, the Rail Repair Plan has seen:<\/p>\n\n\n\n<ul class=\"wp-block-list\"><li>1,536 of 1,900 high-priority defects removed (yearly average from regular trackwork is 600)<\/li><li>800km&nbsp;of track repairs, including grinding and resurfacing<\/li><li>166 electrical backlog inspections completed (surpassing the initial target of 144)<\/li><li>88 speed restrictions removed (repairing the issues that require trains to slow down, like go- slow signs for roadworks)<\/li><li>489 trainstop rams refurbished (vital fail-safe emergency braking systems)<\/li><\/ul>\n\n\n\n<p>While the Sydney Trains network is 150 years old in parts and will never be free from incidents, Sydney Trains\u2019 on-time running data has improved, especially over the past three months.<\/p>\n\n\n\n<p><strong>Transport Minister Jo Haylen said:<\/strong><\/p>\n\n\n\n<p>\u201cKeeping Sydney\u2019s most iconic train line in top condition is no easy feat \u2013 after all, it is 91 years old and needs a bit of extra care.<\/p>\n\n\n\n<p>\u201cI\u2019m thrilled to visit the Sydney Harbour Bridge to personally see the specialised work underway and thank the dozens of workers calling it their office for the weekend to complete these vital upgrades.<\/p>\n\n\n\n<p>\u201cWe are delivering for commuters both above and beneath our Harbour, with both Sydney Trains and Metro work underway to support the people of NSW who travel on our network.<\/p>\n\n\n\n<p>\u201cThis milestone of fixing 80% of high-priority defects well ahead of schedule means we can now get even more work done than we anticipated, and that\u2019s a great outcome for passengers.<\/p>\n\n\n\n<p>\u201cThere will never be a silver bullet to make the Sydney Trains network perfect, but I\u2019m proud to be delivering state\u2019s largest ever program of rail maintenance with real results.\u201d<\/p>\n\n\n\n<p><strong>Sydney Trains Chief Executive Matt Longland said:<\/strong><\/p>\n\n\n\n<p>\u201cThe Harbour Bridge is a key part of our rail network and by investing in this infrastructure, we\u2019re improving reliability for the entire network.<\/p>\n\n\n\n<p>\u201cI\u2019m thrilled to say the Harbour Bridge rail line is the most resilient it\u2019s been in history, with a number of first-time works complete, such as a new airline hose and upgraded overhead wiring.\u201d<\/p>\n\n\n\n<p>\u201cOur peak on-time running is improving, so with the exception of some unavoidable incidents, we\u2019re beginning to see a pattern of more resilient and reliable services for passengers.\u201d<\/p>\n\n\n\n<p>\u201cI want to thank all our passengers for their patience during this time \u2013 while we do our best to limit disruption, this trackwork is essential for a healthy rail network.\u201d<\/p>\n","protected":false},"excerpt":{"rendered":"<p>The Sydney Trains Rail Repair Plan is reaching great heights, as the project hits the halfway mark ahead of schedule with trackwork on the Sydney Harbour Bridge. The $97 million program, announced by the Transport Minister in June to improve the reliability and resilience of the network, has now seen 80% of the 1,900 high-priority &hellip; <a href=\"http:\/\/www.16news.com.au\/index.php\/2023\/12\/04\/rail-repair-plan-hits-halfway-mark-on-a-high\/\" class=\"more-link\">Continue reading<span class=\"screen-reader-text\"> &#8220;Rail Repair Plan hits halfway mark on a high&#8221;<\/span><\/a><\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[4],"tags":[],"class_list":["post-24380","post","type-post","status-publish","format-standard","hentry","category-nswnews"],"_links":{"self":[{"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/posts\/24380","targetHints":{"allow":["GET"]}}],"collection":[{"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/comments?post=24380"}],"version-history":[{"count":1,"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/posts\/24380\/revisions"}],"predecessor-version":[{"id":24381,"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/posts\/24380\/revisions\/24381"}],"wp:attachment":[{"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/media?parent=24380"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/categories?post=24380"},{"taxonomy":"post_tag","embeddable":true,"href":"http:\/\/www.16news.com.au\/index.php\/wp-json\/wp\/v2\/tags?post=24380"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}